ENVIRONMENTAL IMPACT ASSESSMENT (EIA) ACT, CAP EI2, LFN 2004



          An environment impact assessment (EIA) is an assessment of the potential impacts whether positive or negative, of a proposed project on the natural environment the E.I.A. Act, as it is informally called, deals with the considerations of environmental impact in respect of public and private projects.
Sections relevant to environmental emergency prevention under the EIA include:-
1.       Section 2(1): requires an assessment of public or private projects likely to have a significant (negative) impact on the environment.
2.       Section 2(4): requires an application in writing to the agency before embarking on projects for their environmental assessment to determine approval.
3.       Section 13: establishes cases whereby an EIA is required and
4.       Section 60: creates a legal liability for contravention of any provision 
  

ENVIRONMENTAL IMPACT ASSESSMENT: PRINCIPLES AND PRACTICE
The act is basically divided into form parts
Part1- General Principles of Environmental Impact Assessment with broad objectives of:
·               Determination of environmental impacts of activities likely to negatively affect the environment; [s1(a)]
·               Promotion of implementation mechanism at the federal, state and local government levels; [s1(b)]
·               To encourage exchange of data and information as well as consultation and notification of alerts across boundaries to other states, towns and villages[s1(c)]    

 Other Provision Include: (10)
·               Mandatory Assessment – (ss2-3)
These sections make it mandatory that an assessment be made of likely environmental impact or effect an activity would have. This assessment should be made prior to approval of final decision and at the very early stages of the activity.
·                 Disclosure –(ss3,4 and 5)
Section 3 prescribes that significances environment issues shall be identified (disclosed) and studied while sections 4 specify the minimum matters that the environment assessment report must contain:
·                 Consultation [(ss7and 9(2), (3) and (4)]
Prior to giving a decision on any proposed activity, FEPA shall afford concerned professional, government agencies and other stake-holders opportunity to make an input.The consequential report or decisions shall be public
·                 Approval Procedure –[ss6,8,9 (1),10,11(2) and 13)]
The decision of FEPA shall be impartial and given after a minimum time has elapsed, it should also be writing and supported by reasons and details such as conditions for project executions, to any directive for mitigating or that the project should be carried out under supervisions. It may order further investigations into possible hazards.
·                 Participations [s11(1)]
Any parson or community to be affected directly or remotely shall be notified and there shall be “consultations” which in effect means that the parson or community shall have a say in the final decision  of FEPA.

PART II- ENVIRONMENT ASSESSMENT OF PROJECTS
This part basically covers the environment assessment process which  includes:
-        Screening and review and matters incidental hereto (ss16-22)
-        Mandatory study, notices and council’s decisions- (ss23-26)
-        Discretionary powers of the agency, mediation and constitutions of review panel and matters incidental thereto (ss27-39) .
-        Decision of the agency including implementation of mitigation measure follow up programmes and certification (ss40-42)
-        Tran-border matter both domestic and international; international agreements and arrangement; access to information etc. (ss49-59).
  
PART III MISCELLANEOUS
This covers the agency’s power to issue guidelines, codes of practice and facilitating regulations, offence and penalty; interpretation etc. The final part is the schedule which contains the mandatory study activists.
These Include Potential Project in:
·         Agriculture
·         Airport
·         Drainage and irrigation
·         Land reclamation
·         Fisheries
·         Forestry
·         Housing
·         Inducing
·         Infrastructure
·         Ports
·         Mining
·         Petroleum
·         Power generation and transmission
·         Durries.
·         Rail ways
·         Transportation
·         Resort and recreational development
·         West treatment and disposal
·         Water supply.
Legislation that should drive sustainable development. Further more, FEPA has developed detailed procedural sectoral guidelines for case of preparation and assessment of environmental impact report .
This Guidelines Categorised Activates into:
-        Project requiring public review panels extensive public consultation etc.  (FULL EIA)
-        Projects with limited potential environmental impact eg electricity transmission; small scale agro based industries, tourism, rehabilitation of roads etc.
-        Projects likely to have negligible or no potential environmental impacts such as education, family planning, health, nutrition etc. (11)

Approval procedure
As outlined in the procedural guidelines approval procedure involved (12)
a)       NOTIFICATION TO FEPA:
This basically starts with a notification in writing by the submission of the project proposal and completion of the relevant fom (EIA notification form) and payment of N10,000 ($100)
b)       INITIAL EXAMINATION BY FEPA
FEPA then conducts an initial environmental examination (IEE) by considering all relevant information. The project is assigned a category and a screening report is issued and sent to the project proponent.
c)       SUBMISSION OF TERM OF REFERENCE
The project proponent in turn submit its term  of reference covering the environment issues based on site scoping, this is sent back of FEPA.
d)       REVIEW AND HEARING
If FEPA is not satisfied with any issue, it may call for public hearing or ask for further studies.
e)       DRAFT EIA REPORT
When FEPA is finally satisfied the draft EIA report is prepared by the project proponent and submitted to FEPA with a review fee of N240,000 ($2,400)
f)        APPROVAL / “NO PROJECT –DECISION”
If FEPA is satisfied with the EIA report it may either approved or decline approval. If approval is declined, there may be a review process (with a review panel sitting and evidence called by both sides). The review panel will make recommendations on the basis of the hearing.
g)       FINAL EIA REPORT
If approval is given or the review process is in favour of a approval, a final EIA report is submitted to FEPA within 6 months
h       CERTIFICATION
FEPA’s technical committee then issues an environmental impact statement (EIS) along with a certificate
i)        FOLLOW-UP
Some conditions of approval may specify that the project be executed under supervision such supervision and the monitory functions of FEPA will continue possible commissioning.

CHALLENGES AND CONSTRAINTS
The basic challenge confronting FEPA (now federal ministry of environment), is how to translate the laudable provisions of the act into an effective tool for managing the environment. The challenge is crucial because Nigeria, like most developing countries, has world class legislation on various issues, which nevertheless suffers failures at the implementation state.
Experience especially in respect of infrastructure projects has shown that environmental impact assessment is hardly under taken prior to the approval of any project. The case of national stadium Abuja is typical.
The principle enshrined in the act, of pro-active integration of development programme and environmental –friendly projects is observed more in the breach.
The key defaulter in this exercise are the various levels of government; federal, state and local. These levels of government routinely approve projects within the mandatory study list, before any kind of impact assessment is made.  For eg Niger Delta Development Commission (NDDC) in a recent press release had already decided to dredge Ayetoro canal prior to any EIA (13) therefore most EIA reports are actually “post mortem” documents contrived to “fulfil all righteousness” and fence –of resistance from concerned non-governmental organization and affected host communities.
Even where the requisite impact assessments were done the detailed procedure laid down in the act /guidelines were usually forted especially in respect of consultation. Insufficient consultations usually raises anxieties or premature expectations which often manifested in unsubstantiated fears that project may cause adverse impacts or false hopes that projects will bring benefits (14) this is usually “mother” of most community unrest.
A matter currently in the Nigeria high court involves the federal ministry of environment and some coastal communities along the Imo River. The federal government awarded the contract for the dredging of the river, to Nation’s only Aluminium smelting factory at Ikot Abasi. The affected coastal communities stiffly resisted the project on the ground that the draft EIA report was unfavourable to the project. Unknown to them however, the final report got the approval of the ministry and so the dredging project commenced. This represents  a classic failure of consultations and so today the matter is subjudice.
          Further more, the proposal to dredge the river Niger to improve in land water ways, is currently facing resistance from the coastal communities who are demanding compensation for the potential impacts of the project. The federal government only recently declined payment of compensation since it said, the project holds potential economic benefits to the affected communities.
          Finally, the investment climate in Nigeria today is completely receptive of all kinds of investments considered as accessory drive economic growth. This us unwittingly made the country a dumping ground for all kinds of obsolete technologies.
          Poverty and prohibitive costs are often cited as disincentives to importing clean technologies that meet international environmental standards. Governmental for social reasons, appear willing to grant waivers thus diluting the effect of EIA act.
Share on Google Plus

Declaimer - Unknown

The publications and/or documents on this website are provided for general information purposes only. Your use of any of these sample documents is subjected to your own decision NB: Join our Social Media Network on Google Plus | Facebook | Twitter | Linkedin

READ RECENT UPDATES HERE